Developer files $10 million lawsuit against the City of Alachua for delaying development hearings

BY JENNIFER CABRERA

ALACHUA, Fla. – The developer of Tara April, a proposed commercial development on a 58-acre property in the city of Alachua, has sued the City for $10 million plus application expenses, asserting that the City’s failure to schedule an Infrastructure Plan hearing for more than four years has resulted in lost value of the commercial area of the property.

The lawsuit from Tara Forest, LLC, names the City of Alachua and Alachua’s Director of Planning and Community Development Bryan Thomas as plaintiffs. Tara Forest’s attorney Jeff Childers separately sent a demand letter to the City of Alachua in July, requesting public records related to the City’s consideraton of several Tara Forest developments.

The new lawsuit refers to the Tara April development, a 58.3-acre property adjacent to I-75, with 10.50 acres zoned for commercial development and 6.79 acres for conservation uses; the rest of the parcel retained a Recreation designation. The City previously obligated Tara Forest to build, privately own, and privately maintain stormwater treatment for runoff from I-75, with that treatment located on the Recreation-zoned land.

Advertisement

Tara Forest filed its application for the Tara April Infrastructure Plan in 2022, the City determined that it was complete in February 2022, and more than four-and-a-half years later, the City has not issued a decision and has refused to schedule a hearing; under Florida statutes, a municipality “must approve, approve with conditions, or deny the application… within 180 days after the municipality has deemed the application complete.”

According to the complaint, the City required Tara Forest to perform, at its own expense, geophysical evaluation and geologic testing on the Tara April property and two other parcels that Tara Forest has not put forward for development. The evaluation “found no evidence of sinkhole activity or conditions that make the site unsuitable for development.”

However, after Tara Forest provided the City with the geologic testing findings, the complaint states, the City responded with additional objections and still did not schedule a hearing. 

In September, the City reportedly told Tara Forest in a letter that it could not schedule a hearing because a stormwater management facility “cannot exist as a principal use.” According to the complaint, the letter “cited no ordinance, rule, statute, or other legal authority for refusing to schedule a hearing.”

The complaint states that the City’s “stubborn refusal to hold a hearing on the Tara April Infrastructure Plan” has cost Tara Forest $500,000 in application expenses and $10 million in lost value of the commercial area to be developed within Tara April.

The complaint states that “[f]urther application to the City is futile, and any administrative remedy the City may identify is neither adequate nor available… There is no further step available to Tara Forest within the City’s process that could produce a decision or force a hearing without this Court’s involvement.”

The complaint notes that additional claims are pending when the statutory requirements for bringing those claims are satisfied. 

The lawsuit asks the Court for a writ of mandamus that requires the City to process the application for approval or denial; declaratory judgment regarding open questions about the City’s Land Development Regulations, specifically whether the City is obligated to provide a hearing and that the requirements to conduct studies on other parcels are not authorized; an injunction that prevents the City from making the studies on the other parcels a condition for holding a hearing on Tara April; and compensation for depriving Tara Forest of the use and development of the property for over four years.

Tara Forest has also filed a separate lawsuit regarding the City’s failure to provide public records; according to the court docket, no hearing has been scheduled in response to Tara Forest’s September 21 motion to set an immediate hearing. 

2 Comments